ADAM ES ADDITIONS AND RENOVATIONS
Download Project Status Report
Architect: VLK
Contract Amount: $14,680,000
Contractor: Prime Contractors, Inc.
Notice to Proceed: 4/21/16
CFISD PM: Steven Johnson
Substantial Completion Projected: 8/11/2017
Substantial Completion Actual: 8/25/17
Punch
50%
Warranty
N/A
DRL
90%
% Complete: 100%
SCOPE OF WORK
Projected project scope is to build an addition to Adam ES and perform renovations to the existing site.
Milestones – Construction Phase
Board Approval – 5/16/16
Notice to Proceed – 5/17/16
Pre-Construction – 5/18/16
Construction: Phase 1 – 6/6/16 – 8/11/17 (Detention Pond, New Additions, Site Work, etc.)
Construction: Phase 2 – 6/6/16 – 8/12/16 (Abatement, Above Ceiling Work, etc.)
Construction: Phase 3 – 5/30/16 – 8/11/17 (Interior Renovations, Site Work, Canopy, etc.)
Substantial Completion Date – 8/11/17
Close Out: 2/16/18
Scope of Work Completed
Architectural/Activities/Food Service:
Replaced existing lay-in ceiling tile and grid throughout the facility
Replaced walking track & basketball court
Provided new canopy at entry
New LED lighting throughout the campus
New Building Controls
New Cat6 cabling
New walls and teaching walls
New carpet throughout the campus
New casework throughout the campus
Approximately 15,000 SF classroom and admin addition
Approximately 6,000 SF kitchen addition and kitchen renovation
New doors and hardware
Civil/Fire & Life Safety:
Installation of new fire sprinkler system throughout the facility
Structural Spray Asphalt Parking Lot
Detention Pond
Security
New secure entry with bullet resistant glass
New lockdown panic buttons
New PA system
New security system including camera replacement